| MILESTONE |
STATUS
(Not Started/ In Progress/ Completed) |
| Site clearing and timbering west of Gum Spring Road (Rt. 659)
|
Completed
|
| Removal of overburden* west of Gum Spring Road
|
In Progress
|
| Construction of overburden area C
|
Not Started
|
| Seeding and planting of overburden area C
|
Not Started
|
| Construction of the new Gum Spring Road, Started Fall 2010
|
In Progress
|
| Construction of a new berm along the new Gum Spring Road
|
In Progress
|
| Seeding and planting of the berm along Gum Spring Road
|
In Progress
|
| Rerouting of traffic to the new Gum Spring Road Estimated March 2012
|
Not Started
|
| Construction of a new entrance to the quarry
|
In Progress
|
| Construction of a new processing center
|
Not Started
|
| Razing of the existing processing center
|
Not Started
|
| Construction of wetlands Estimated January 2012
|
Not Started
|
| Construction of overburden area B
|
Not Started
|
| Seeding and planting of overburden area B
|
Not Started
|
| Construction of overburden area A
|
Not Started
|
| Seeding and planting of overburden area A
|
Not Started
|
| Construction of berm along southeast corner of property
|
Not Started
|